SPAS 00001 Published On: 09/12/2022
Question: 4.2.b requires “Have a physical location in DESC Balancing Authority Area and be physically interconnected to the DESC transmission system or distribution system.” However as can be seen from our initial submittals, that our 75MWac Evergreen project is located in Kershaw County outside, although near to DESC transmission system, is outside of the DESC Balancing authority. Will we be allowed to proceed and be considered?
Answer: Projects that are physically outside the BAA may be considered if they interconnect with the Dominion Transmission system directly.
SPAS 00003 Published On: 04/01/2024
Question: Have any projects been awarded for the Urquhart RFP thus far, or are we still in the evaluation phase since December 2022, and this new RFP is just a continuation of that?
Answer: The 2023-2024 reissuance of this RFP is a continuation of the original RFP. Based on the reissuance, there are no existing awards and any future awards will be made after the evaluation process is complete pursuant to the reissued RFP.